On 22 June 2012 05:03, Kyotaro HORIGUCHI
<horiguchi.kyotaro@lab.ntt.co.jp> wrote:
> I hope this is promising.
I've reviewed this and thought about it over some time.
At first I was unhappy that you'd removed the restriction that
timelines only change on a shutdown checkpoint. But the reality is
timelines change at any point in the WAL stream - the only way to tell
between end of WAL and a timeline change is by looking for later
timelines.
The rest of the logic seems OK, but its a big thing we're doing here
and so it will take longer yet. Putting all the theory into comments
in code would certainly help here.
I don't have much else to say on this right now. I'm not committing
anything on this now since I'm about to go on holiday, but I'll be
looking at this when I get back.
For now, I'm going to mark this as Returned With Feedback, but please
don't be discouraged by that.