How to ensure a log-entry is created based on state of data in other tables
How to ensure a log-entry is created based on state of data in other tables
Hi.
I'm not sure what the best subject is for this email, but here are the requirements: When all activities for a given product has status='DONE' then an entry in activity_product_log should be created. This should be guaranteed somehow. If an activity for which there exists an entry in activity_product_log is set to status='NOT_DONE', then the entry in activity_product_log should be deleted.
Here's an example-schema:
DROP TABLE IF EXISTS activity_product_log;
DROP TABLE IF EXISTS activity;
DROP TABLE IF EXISTS product;
CREATE TABLE product
(
id INTEGER primary key,
name varchar not null unique
);
CREATE TABLE activity
(
id serial primary key,
name varchar not null unique,
product_id integer not null references product(id),
status varchar NOT NULL,
CHECK (status IN ('NOT_DONE', 'DONE'))
);
CREATE TABLE activity_product_log
(
id serial primary key,
product_id integer not null references product(id),
created TIMESTAMP NOT NULL
);
INSERT INTO product(id, name) VALUES(1, 'Horse'), (2, 'Fish');
INSERT INTO activity(name, product_id, status)
VALUES ('A1', 1, 'NOT_DONE'), ('A2', 1, 'NOT_DONE'), ('A3', 1, 'NOT_DONE'), ('A4', 1, 'NOT_DONE')
, ('A5', 2, 'NOT_DONE'), ('A6', 2, 'NOT_DONE')
;
UPDATE activity SET status = 'DONE' WHERE name = 'A1';
UPDATE activity SET status = 'DONE' WHERE name = 'A2';
UPDATE activity SET status = 'DONE' WHERE name = 'A3';
UPDATE activity SET status = 'DONE' WHERE name = 'A4'; -- Here an entry in activity_log should be created
I'm thinking about using constraint-triggers for this but will that actually guarantee the requirements? I'm worried about the last part of the requirement, if all activities for a product are ‘DONE’ but then gets toggled ‘NOT_DONE’ and ‘DONE’ “very fast”.
Is there a better way, using some extra tables to do bookkeeping can the have constraints ensuring this business-requirement?
Re: How to ensure a log-entry is created based on state of data in other tables
Hi.
I'm not sure what the best subject is for this email, but here are the requirements: When all activities for a given product has status='DONE' then an entry in
activity_product_logshould be created. This should be guaranteed somehow. If an activity for which there exists an entry inactivity_product_logis set to status='NOT_DONE', then the entry inactivity_product_logshould be deleted.
Here's an example-schema:
DROP TABLE IF EXISTS activity_product_log;
DROP TABLE IF EXISTS activity;
DROP TABLE IF EXISTS product;
CREATE TABLE product
(
id INTEGER primary key,
name varchar not null unique
);
CREATE TABLE activity
(
id serial primary key,
name varchar not null unique,
product_id integer not null references product(id),
status varchar NOT NULL,
CHECK (status IN ('NOT_DONE', 'DONE'))
);
CREATE TABLE activity_product_log
(
id serial primary key,
product_id integer not null references product(id),
created TIMESTAMP NOT NULL
);
INSERT INTO product(id, name) VALUES(1, 'Horse'), (2, 'Fish');
INSERT INTO activity(name, product_id, status)
VALUES ('A1', 1, 'NOT_DONE'), ('A2', 1, 'NOT_DONE'), ('A3', 1, 'NOT_DONE'), ('A4', 1, 'NOT_DONE')
, ('A5', 2, 'NOT_DONE'), ('A6', 2, 'NOT_DONE')
;
UPDATE activity SET status = 'DONE' WHERE name = 'A1';
UPDATE activity SET status = 'DONE' WHERE name = 'A2';
UPDATE activity SET status = 'DONE' WHERE name = 'A3';
UPDATE activity SET status = 'DONE' WHERE name = 'A4'; -- Here an entry in activity_log should be createdI'm thinking about using constraint-triggers for this but will that actually guarantee the requirements? I'm worried about the last part of the requirement, if all activities for a product are ‘DONE’ but then gets toggled ‘NOT_DONE’ and ‘DONE’ “very fast”.
Is there a better way, using some extra tables to do bookkeeping can the have constraints ensuring this business-requirement?
Re: How to ensure a log-entry is created based on state of data in other tables
[…]
What is the time window required for "DONE" and "NOT_DONE" to be correct? Do they need to be atomic (meaning the time window is effectively 0)? Or can the system "notice" recent changes and keep track of done/not done after-the-fact? If your time window is > 0, it seems like recurring processes could be set up to track DONE / NOT_DONE?Another totally different way to think about this is to create a view that provides answers on DONE and NOT_DONE as computed values based on the underlying state of the table at the time the view is queried? That would seem to satisfy a time window of 0?Steve
Yes, they need to be atomic. Either all are DONE and there is an entry in activity_product_log for product_id, or there is no entry in activity_product_log.
Re: How to ensure a log-entry is created based on state of data in other tables
På torsdag 09. februar 2023 kl. 16:08:16, skrev Steve Midgley <science@misuse.org>:[…]
What is the time window required for "DONE" and "NOT_DONE" to be correct? Do they need to be atomic (meaning the time window is effectively 0)? Or can the system "notice" recent changes and keep track of done/not done after-the-fact? If your time window is > 0, it seems like recurring processes could be set up to track DONE / NOT_DONE?Another totally different way to think about this is to create a view that provides answers on DONE and NOT_DONE as computed values based on the underlying state of the table at the time the view is queried? That would seem to satisfy a time window of 0?SteveYes, they need to be atomic. Either all are DONE and there is an entry in
activity_product_logforproduct_id, or there is no entry inactivity_product_log.
Re: How to ensure a log-entry is created based on state of data in other tables
Is there a better way, using some extra tables to do bookkeeping can the have constraints ensuring this business-requirement?
Re: How to ensure a log-entry is created based on state of data in other tables
Hi.
I'm not sure what the best subject is for this email, but here are the requirements: When all activities for a given product has status='DONE' then an entry in
activity_product_logshould be created. This should be guaranteed somehow. If an activity for which there exists an entry inactivity_product_logis set to status='NOT_DONE', then the entry inactivity_product_logshould be deleted.
Here's an example-schema:
DROP TABLE IF EXISTS activity_product_log; DROP TABLE IF EXISTS activity; DROP TABLE IF EXISTS product; CREATE TABLE product ( id INTEGER primary key, name varchar not null unique ); CREATE TABLE activity ( id serial primary key, name varchar not null unique, product_id integer not null references product(id), status varchar NOT NULL, CHECK (status IN ('NOT_DONE', 'DONE')) ); CREATE TABLE activity_product_log ( id serial primary key, product_id integer not null references product(id), created TIMESTAMP NOT NULL ); INSERT INTO product(id, name) VALUES(1, 'Horse'), (2, 'Fish'); INSERT INTO activity(name, product_id, status) VALUES ('A1', 1, 'NOT_DONE'), ('A2', 1, 'NOT_DONE'), ('A3', 1, 'NOT_DONE'), ('A4', 1, 'NOT_DONE') , ('A5', 2, 'NOT_DONE'), ('A6', 2, 'NOT_DONE') ; UPDATE activity SET status = 'DONE' WHERE name = 'A1'; UPDATE activity SET status = 'DONE' WHERE name = 'A2'; UPDATE activity SET status = 'DONE' WHERE name = 'A3'; UPDATE activity SET status = 'DONE' WHERE name = 'A4'; -- Here an entry in activity_log should be createdI'm thinking about using constraint-triggers for this but will that actually guarantee the requirements? I'm worried about the last part of the requirement, if all activities for a product are ‘DONE’ but then gets toggled ‘NOT_DONE’ and ‘DONE’ “very fast”.
Is there a better way, using some extra tables to do bookkeeping can the have constraints ensuring this business-requirement?
Is there any ordering or workflow associated?
Does the product (or perhaps product type) define number of activities (or list of "activity.name"s). Is there no "activity type"?
Can a product be "DONE" more than once? If not perhaps the product table should have the status field?
Re: How to ensure a log-entry is created based on state of data in other tables
Is there a better way, using some extra tables to do bookkeeping can the have constraints ensuring this business-requirement?
Every time an activity newly becomes "Not Done" increment a "not done seen counter" and likewise with a "done seen counter". Whenever the former is greater than the later you have one or more not done activities.David J.
Ah, this is what I'm looking for, I think.