The new server ... light at end of tunnel ...

Поиск
Список
Период
Сортировка
Искать

The new server ... light at end of tunnel ...

От:
"Marc G. Fournier" <scrappy@postgresql.org>
Дата:

Just waiting on final quote, which will hopefully be this aft, to make the 
order ... the new server will be a Dual-Athlon, 6x36G Seagate drives, etc, 
etc ...

Just to give an idea of what the plans/scheduale looks like:

Once parts arrive, my contact is going to do a 48hr burn in, just to make 
sure there are no readily apparent problems ... then, he's going to ship 
it out directly down to Panama (he's in San Francisco) ... based on past 
experiences, figure on 5 days from SF->Co-lo facility, figuring on customs 
delays and such ...

Assuming hardware arrives intact, I have someone down there that will be 
doing a base install of the OS for me, and getting it onto the network for 
me to work on remotely ... I'll do the OS upgrade, and get the final 
configuration stuff in place ... usually, 24hrs ...

Once that's done, then the VMs start moving ... that is the slow process 
of the bunch, since its basically 'one VM at a time' so as to minimize 
downtime per VM ...

That said ... I know pgFoundry needs its shell VM created, which will be 
done as soon as we get the new server online ... are there any other 
projects that need anything special done for them?

----
Marc G. Fournier           Hub.Org Networking Services (http://www.hub.org)
Email: scrappy@hub.org           Yahoo!: yscrappy              ICQ: 7615664